Case Study: Castle Group – Level 1 Office Upgrade

Client: Castle Group | Location: Brookhollow Avenue, Norwest

Project Overview

Castle Group required a full upgrade of their 650sqm “Stage 1” office floor on Level 1 to accommodate their 80 staff members. DNP Projects delivered a construction-only fitout that transformed the existing space into a modern, functional, and collaborative workplace.

Brief & Objectives

The goal was to create a fully refreshed office environment while retaining only five existing offices, repurposed into new meeting rooms. Key objectives included:

  • Optimising space for 80 staff members

  • Enhancing collaboration and circulation with curved half-height walls

  • Integrating modern technology and security

  • Delivering a functional, aesthetically appealing environment on a tight timeline

Scope of Works

  • Full demolition of the 650sqm floor (10 truck trips)

  • Conversion of existing offices into new meeting rooms

  • Curved half-height walls to improve entry flow

  • Fully integrated security systems

  • Collaboration with in-house Design Manager Ric Ranieri

  • New 3-piece kitchen joinery with stone benchtops

  • Flooring throughout: acoustic carpet tiles and vinyl in wet areas

  • Painting throughout the suite

  • Upgraded blinds and installation of TVs in meeting rooms

  • Additional electrical works including data and power for 60+ workstations

Delivery & Outcome

The project commenced in early December and was completed by 7th January, meeting Castle Group’s requested timeline. The upgraded office now supports staff productivity and collaboration while offering a modern, comfortable workplace. The seamless transition into the new space demonstrates careful planning, efficient construction, and collaborative design execution.